Station Avenue Complete Streets

Reconstruction of Station Avenue in downtown Millbrook with wider sidewalks, a two-way separated bike lane, bus bulbs, and new crossings. Completed in November 2025.
Current phase
Completed
Completed
November 2025
Estimated cost
$14.3 million
Jurisdictions
City of Millbrook

Current phase

  1. Planning (complete)
  2. Environmental Review (complete)
  3. Design (complete)
  4. Procurement (complete)
  5. Construction (complete)
  6. Completed (current phase)

Purpose and need

Improve safety and access on Millbrook's main transit street, where narrow sidewalks and wide crossings contributed to pedestrian crashes near the Transit Center.

Project overview

Station Avenue connects the Millbrook Transit Center, the Community Center, and the downtown business district. Before reconstruction, the street had narrow sidewalks, no bicycle facilities, and four unsignalized crossings with a history of pedestrian crashes.

Completed improvements

  • 0.9 miles of roadway reconstruction with a road diet from four lanes to two lanes and a center turn lane
  • Two-way separated bike lane connecting to the Millbrook Creek Trail
  • Two bus bulbs serving Ridge Transit Routes 4 and 17
  • Four new high-visibility crossings, including one pedestrian hybrid beacon
  • Street trees, pedestrian lighting, and green stormwater planters

Project closeout

Final acceptance was approved in November 2025. The closeout report, including before-and-after traffic counts and a one-year crash review schedule, is available below.

Project updates

  • Project complete

    The Board accepted the project as complete. A one-year post-construction safety review will be presented to the Technical Advisory Committee in late 2026.

  • Station Avenue fully reopened

    All lanes, sidewalks, and the separated bike lane are open. Final landscaping will be completed in spring 2026 under the plant establishment period.

Public involvement

  • Design workshops

    Two workshops and a business owner meeting shaped the final cross-section and parking changes.

Timeline and milestones

  1. Concept plan approved, complete

    2020

  2. Environmental clearance, complete

    2021

  3. Final design, complete

    2022

  4. Construction, complete

    April 2024–October 2025

  5. Final acceptance and closeout, complete

    November 2025

Funding

Funding sources for Station Avenue Complete Streets
SourceAmount
Surface Transportation Block Grant Program (STBG)Federal$7,800,000
Transportation Alternatives Set-Aside (TA)Federal$1,900,000
Regional Transportation Improvement FundLocal$2,900,000
City of MillbrookLocal$1,700,000
Total project cost$14,300,000