Construction notice: Harlan Avenue (Route 17) Lane Closures: Norfolk Street to Cedar Road. Closure details: Harlan Avenue (Route 17) Lane Closures: Norfolk Street to Cedar Road

Capital project NRTA-C-0149Environmental Review

Lakemont Station Area Pedestrian Safety Improvements

Crossing, sidewalk, and lighting improvements within a half mile of the Lakemont Transit Center, including the Lake Street and 4th Avenue intersection.
Current phase
Environmental Review
Expected completion
2028
Estimated cost
$6.8 million
Jurisdictions
City of Lakemont, Stanton County

Current phase

  1. Planning (complete)
  2. Environmental Review (current phase)
  3. Design (not started)
  4. Procurement (not started)
  5. Construction (not started)
  6. Completed (not started)

Purpose and need

Address a cluster of pedestrian crashes, including two fatalities, on the High Injury Network segment serving the Lakemont Transit Center.

Project overview

The Regional Safety Action Plan identified the area around the Lakemont Transit Center as part of the region's High Injury Network. Seven pedestrian crashes, two of them fatal, occurred within a quarter mile of the transit center between 2020 and 2024.

Proposed improvements

  • Curb extensions and a leading pedestrian interval at Lake Street and 4th Avenue
  • A rectangular rapid flashing beacon crossing at Lake Street and Grove Street
  • 1.3 miles of new or widened sidewalk
  • Pedestrian-scale lighting on 4th Avenue

Project updates

  • Environmental review begins

    Staff have begun environmental documentation. A community walk audit with residents is planned for October 2026.

Public involvement

  • Upcoming

    Community walk audit

    Residents are invited to walk the station area with project staff and City of Lakemont engineers. Meets at the Transit Center, 10:00 a.m.

  • Upcoming

    Draft plan workshop in Lakemont

    Project staff will be available at the Lakemont workshop for the Draft 2050 Regional Transportation Plan.

Timeline and milestones

  1. Grant award, complete

    2025

  2. Environmental review, in progress

    2026

  3. Design, upcoming

    2027

  4. Construction, upcoming

    2028

Funding

Funding sources for Lakemont Station Area Pedestrian Safety Improvements
SourceAmount
Safe Streets and Roads for All (SS4A)Federal$4,900,000
City of LakemontLocal$1,200,000
Regional Transportation Improvement FundLocal$700,000
Total project cost$6,800,000